Cabinet Approves ₹14,500-Crore VGF Scheme for 92 GWh Grid-Scale Energy Storage
• The Union Cabinet approved a ₹14,500-crore Viability Gap Funding scheme for grid-scale energy storage for FY 2026-27 to FY 2030-31.
• The programme targets 92 GWh of new capacity: 60 GWh pumped hydro, 30 GWh battery storage and 2 GWh alternative technologies.
• Estimated investment is ₹97,600 crore; BESS projects must meet a 40% domestic content requirement.
• Capacity will be allotted through tariff-based competitive bidding to support renewable integration and grid stability.
The Union Cabinet, chaired by Prime Minister Narendra Modi, has approved a Viability Gap Funding scheme of ₹14,500 crore to build 92 GWh of grid-scale energy storage capacity between FY 2026-27 and FY 2030-31.
The scheme is designed to accelerate renewable-energy integration, strengthen grid stability and support reliable, affordable round-the-clock power. Officials said the new capacity would equal about 170% of present-day grid-scale storage and help India progress toward an estimated requirement of 411 GWh of grid-scale energy storage systems by 2031-32.
Of the 92 GWh, 60 GWh is earmarked for hydro pumped storage plants, 30 GWh for battery energy storage systems and 2 GWh for emerging alternative storage technologies. Total project investment is estimated at ₹97,600 crore. VGF support is meant to improve project bankability so that storage can be built at scale alongside solar and wind capacity.
Energy storage capacity will be allocated through tariff-based competitive bidding. Public and private distribution companies will be eligible for VGF for battery and pumped-hydro projects, while alternative-technology projects may be taken up by public and private entities. Battery projects will carry a minimum 40% domestic content requirement to spur local manufacturing and cut import dependence.
By firming variable renewable generation, storage reduces the need for conventional plants to provide balancing power and can lower curtailment of green energy. The Cabinet framed the scheme as part of Atmanirbhar Bharat and Viksit Bharat goals, pairing demand-side funding with India’s existing supply-side battery manufacturing incentives.